How to adjust the Gantt settings (Cog)

Table of Contents

To make changes to the Gantt view, click on the Cog button in the top bar and choose your preferred settings:

Top Tip

  • Changes made via the Gantt settings cog are user specific. Any changes will only impact your own view.
 
  • Show Critical Path:  the critical path will be highlighted in red (both critical tasks and dependency links - not milestones). Note: This setting must be used in conjunction with auto-scheduling to work.
  • Show Slack: display slack between tasks on the Gantt (shaded grey). This is useful to see if using auto-scheduling.
  • Show Dependencies: display dependency lines between tasks and milestones.
  • Set Date Range: tick and select to view a specific date range.
  • Columns: The Gantt will by default show you all available columns on the left-hand side. Untick these to filter out certain columns when not required on screen.